Proposed Element Naming Convention for CBETA All element names will use 8 characters All characters will be upper case. Format: *TSSCCCNN*_signal_name where: T =...
CBETA Equipment Protection System *Responsible personnel: Nalanjan Banerjee, Adam Bartnik, John Dobbins, Karl Smolenski, Rob Michnoff, and others*Date: February x...
CBETA FFAG Magnets and Girders Halbach Magnet Measurement and Tuning * Summary results of production run (Stephen Brooks): CBETA note 035 * Magnet measurem...
CBETA Fractional Arc Test Magnet and Beam Pipe Layout The magnet and beam pipe layout for the fractional arc test splitter line and first FFAG girder is defined ...
CBETA Splitters Splitter line magnet polarity convention For bipolar dipole magnets: * Horizontal: Positive current = beam to the outside of the ring * Ver...
CBETA Supporting Documents and Presentations CBETA Publications and tech notes can be found elsewhere at the links below * Publicatons: https://www.classe.cor...
CBETA System Tests FFA Corrector Power Supplies and Magnetic Field Checks * Responsible personnel: xxxx * Date: February xx, 2019 Description of test Con...
CBETA System Tests Splitter Power Supply and Magnetic Field Checks * Responsible personnel: xxxxx * Date: February xx, 2019 Description of test Confirm t...
CBETA V, the Virtual Machine, and EPICS CBETA V CBETA V is a custom version of Tao, written by David Sagan. It has all of the normal functionality of Tao, but wi...
CBV (CBETA Viewer) CBV is the primary way of viewing both real and virtual machine BPM data, and other optics functions from the virtual machine. It is still in h...
Main.AdamBartnik 07 Mar 2018 The CBETA accelerator will be assembled and commissioned in phases according to the following plan: 1 MLC test * Commissioni...
Main.acb20 07 Mar 2018 Laser Synchronization Find the DOOCS control screen * First open the JDDD interface to the laser synchronization * Either type ....
Main.JamesCrittenden 18 Jan 2020 Tuning at the beginning of the shift Open the strip tool files /home/erpopr/mlc/striptool_files/MLC_piezo_cntrl_vltg.stp and /h...
Main.AdamBartnik 07 Mar 2018 Find the Gate Valve EDM Screen * From the main EDM window, choose "Vacuum" "Gate Valve Control" * The following window will ...
The simGUI interface to GPT simGUI is the result of many years of development towards a user friendly GUI to interact with GPT and other (Astra, BMAD...) simulati...
Main.AdamBartnik 07 Mar 2018 Find the laser power control screen * From the main EDM screen, choose "Laser" and "Laser Power" : * A screen will open up...
Viewscreens Both the viewscreens for the beam and the cameras to monitor the laser all follow the same strategy. 1. Viewscreen is inserted via an EPICS command...
The primary project goal is to provide 4 pass acceleration of 1 mA beam to 150 MeV, then decelerate in 4 passes and dump. The energies are defined as follows: ...